Pavan Kumar
Hi Team,
what is the best approach we can follow for 8.5.6 old instances when we move to BAW19.
I think after moving to BAW convert HHS to CSHS and make sure it is working properly then redeploy to production with not migrating old instances . is this the only option or we can migrate old instances ?
Pavan Kumar
can anyone provide inputs on this?\
Thanks in advance
SPARK Support
Hi Pavan,
Any Process Application that has been developed using SPARK UI in BPM version 8.5.6 should be evaluated for potential issues when upgrading a server to any version of BAW. The best practice would be to dedicate time and resources to migrating all instances of SPARK UI to the current version of the stock UI Toolkit.
Salient Process offers services on an engagement basis to help clients migrate to BAW from older versions of BPM. We can also help to expedite migrations with much less development time using proprietary tools. Please contact our Sales Team if you are interested in having a discussion about how we can help to automate your migration.
Regards,
Stephen P.